231: Unaware of SPAC

Node Unaware of SPAC

Definition/Typical Issues

Were standards, directives, or policies not communicated from management down through the organization?

Note 1: In addition to the node number, the company- or facility-specific SPAC may also be coded in the trending database to aid in trending of causes. For example:

  • If the root cause is the No SPAC or Issue Not Addressed in SPAC (#226) node; and
  • The issue is that the facility's procedure guidelines (say it's plant policy AD-01.7) only requires field validation of safety-related procedures, but not quality-related procedures; and
  • As a result of a procedure error that could have been corrected during field validation, unacceptable product was sent to a customer.

In addition to coding the root cause of No SPAC or Issue Not Addressed in SPAC (#226), AD-01.7 should also be entered into the trending database. This will allow the facility to specifically identify the SPAC that is associated with each root cause.


Examples

Example 1

  • During an extended facility outage, routine surveillances of process alarm panels were not performed. As a result, a chemical leak went undetected for 2 days. Facility management had not communicated to first-line supervisors that normal surveillance procedures remained in effect during the outage.

Example 2

  • The corporate reliability group set up a database to capture field problems. However, facility personnel were not made aware of the new system. As a result, the database was not populated.

Example 3

  • A standard was in place that addressed the use of storage racks. The standard was not applied because personnel were unaware it existed. As a result, the storage racks were undersized.

Typical Recommendations

  • Review the contents of relevant SPACs during initial and refresher training; assess employees' understanding.
  • Periodically stress the importance of using SPACs during shift-change meetings, safety meetings, etc.
  • Ensure that SPAC documentation is readily available to all affected employees at all times.

Cross-References

Version 10 Element(s)
Node ID Node Name
69 Communication of SPACs LTA

 

RBPS Element(s)
Process Safety Culture

 

Maritime Element(s)
Node ID Node Name
263 Unaware of SPACs
Back to top